Sharing knowhow in offshore wind construction

Extreme mobilising

By Glen Andresen, Senior Manager, Project Engineering

A2SEA has done plenty of mobilisations over the years. But never one quite like the recent makeover of SEA INSTALLER for West of Duddon Sands. It was the biggest mobilisation we have ever attempted – both in time, in effort and in the sheer number of people involved. Continue reading

26,000 leg operations without putting a foot wrong

By Hans Peter Johannsen, Senior Project Manager and Head of Engineering

Many thousands of jack-up operations. No leg bends, no punch-throughs. It’s an achievement that goes against the laws of nature. Yet sure-footed legwork over more than a decade is a key A2SEA competency – and proof that the impossible really can be done. Continue reading

Report from Gwynt y Môr

By Steen Drue, Project Manager, A2SEA A/S

Turbine installation work at Gwynt y Môr began on April 30 when SEA JACK started work loading components for the very first of 160 turbine locations. Seven weeks later, SEA WORKER departed from Grenaa, Denmark, headed for the port of Mostyn to join the installation teamwork. In June, the two vessels began working ”side-by-side”, although, in reality, they only occasionally pass each other on the water. Continue reading

The first installation vessel with pre-loaded know-how

SEA INSTALLER

Designed on the basis of the knowledge and experience gained from installing over 800 turbines and more than 400 foundations, A2SEA’s SEA INSTALLER is one of the offshore wind industry’s most sophisticated installation vessels. To find out what makes the SEA INSTALLER so special, we talked to Hans Peter Johannsen, Head of Engineering and Senior Project Manager at A2SEA. Continue reading

Customers talk about challenges

With offshore wind developments in the UK currently generating more power than the rest of Europe combined, and a strong pipeline of projects planned for the coming decade, offshore wind has become a major element in the UK energy mix.

In the Irish Sea, home to two of the Round 3 zones, locating a harbour with enough storage capacity to stock huge turbines and foundations, and deep enough for large installation vessels to operate, were two major challenges facing both DONG Energy and RWE. Continue reading